Current Progress:

Earth works are completed with the house sites prepared. 

90% of sewerage connections were completed before the lock down and our contractors are back as of 5 May.

Stormwater connections will be completed by the end of May and we plan to start the concreting of the internal road early June. 

image8

2020

Retirement Village Stage 1 - 22 unit development begins.


Common facilities - Constructed in parallel . Club room, Hobby room, BBQ area, Greenhouse,  Pétanque court.


2021

Continuation of Stage 1


2022

Retirement Village Stage 2 - A further 23 units.


2023

Rest Home - Construction of the 40 bed rest home facility with hospital level care.


2024

Retirement Village Stage 3

A further 22 units.

 

Future Plans
Rest Home
Expansion of the rest home to 80 beds.
Construction of serviced apartments.